Item/Task | Owner | sub-item/task | Dates | Comment |
---|---|---|---|---|
FEB | Ben | |||
layout | Done 8/4 | |||
fabrication | 8/6-8/12 | |||
loading | 8/13-8/20 | |||
testing | 8/21- | |||
L4-6 Half-module production | Tim | |||
apv25 loading | 8/7 | |||
hybrid & sensor QA | 8/12 | |||
half-module production incl. QA | 8/19-8/29 | When Tim is back. | ||
L1-3 Module assembly | Tim | |||
L4-6 Module assembly | Tim | |||
Mechanical dry run assembly | Shawn | |||
w/o cabling and real FEBs (but cold plate) | 8/8 | |||
Motion control system check | Takashi | 8/15 | ||
Survey | Tim/Takashi/John | overview and procedures needed | ||
Modules | ||||
U-channels | ||||
SVT full assembly survey | ||||
Internal cabling | Tim/Dave | |||
Magnet wire signal transmission test | done | |||
Magnet wire high voltage test | 8/8 | Pelle will do it. | ||
FEB mezzanine card layout | 8/8 | |||
FEB mezzanine card fabrication | 8/15 | |||
Hybrid mezzanine card layout | 8/13 | |||
Hybrid mezzanine card fabrication | 8/20 | |||
pre-production bundle assembly | 8/21-8/26 | |||
pre-production bundle test with FEB | 8/27-9/3 | |||
production bundle assembly | 9/4-9/12 | |||
FEB power bundle design | done | |||
FEB power bundle assembly | 8/26 | Need cable length estimate. 2 days of shop work. | ||
FEB high voltage bundle design | done | |||
FEB power bundle assembly | 8/26 | Need cable length estimate. 2 days of shop work. | ||
External cabling & Power | Pelle | |||
High voltage | 8/22 | 2/3 bundles done. Waiting for more wire. | ||
Low voltage | Done. | |||
PS checkout | Done. | |||
PS epics control | 9/1 | Can control through backup interface until ready. | ||
Power flange | Pelle | |||
Fabrication | 8/8 | One spare included. | ||
Testing with FEB and PS | 8/8 | Need dummy connector on power. High voltage with banana plugs? | ||
Signal flange | Pelle | |||
Fabrication | ||||
Chiller and cooling system | ||||
Target | Clive/Marco | |||
Design | ||||
Fabrication | ||||
Testing | ||||
14. flange cards 15. outer power cables 16. Chiller and cooling system checkout 17. PS checkout 18. Shipping boxes