Item/TaskOwnersub-item/taskDatesComment
FEBBen
 
  
  layout

Done 8/4

 
  fabrication8/6-8/12 
  loading8/13-8/20 
  testing8/21- 
L4-6 Half-module productionTim   
  apv25 loading8/7 
  hybrid & sensor QA8/12 
  half-module production incl. QA8/19-8/29When Tim is back.
L1-3 Module assemblyTim   
L4-6 Module assemblyTim   
Mechanical dry run assemblyShawn   
  w/o cabling and real FEBs (but cold plate)8/8 
Motion control system checkTakashi 8/15 
SurveyTim/Takashi/John  overview and procedures needed
  Modules  
  U-channels  
  SVT full assembly survey  
Internal cablingTim/Dave   
  Magnet wire signal transmission testdone 
  Magnet wire high voltage test8/8Pelle will do it.
  FEB mezzanine card layout8/8 
  FEB mezzanine card fabrication8/15 
  Hybrid mezzanine card layout8/13 
  Hybrid mezzanine card fabrication8/20 
  pre-production bundle assembly8/21-8/26 
  pre-production bundle test with FEB8/27-9/3 
  production bundle assembly9/4-9/12 
  FEB power bundle designdone 
  FEB power bundle assembly8/26Need cable length estimate. 2 days of shop work.
  FEB high voltage bundle designdone 
  FEB power bundle assembly8/26Need cable length estimate. 2 days of shop work.
External cabling & PowerPelle   
  High voltage8/222/3 bundles done. Waiting for more wire.
  Low voltageDone. 
  PS checkoutDone. 
  PS epics control9/1Can control through backup interface until ready.
Power flangePelle   
  Fabrication8/8One spare included.
  Testing with FEB and PS8/8Need dummy connector on power. High voltage with banana plugs?
Signal flangePelle   
  Fabrication  
     
     
Chiller and cooling system    
     
     
TargetClive/Marco   
 Design   
 Fabrication   
 Testing   
     
     
     
     

 14. flange cards 15. outer power cables 16. Chiller and cooling system checkout 17. PS checkout 18. Shipping boxes