- Configuration files (LATc, LCI, etc) (JHP, LHM)
- Jim & Byron's LATTE -> LICOS XML conversion tool
- Addition of FMX headers
- Verification of file upload (processing telemetry from diagnostic stream)
- MOOT/MOOD status (API definition)
- Archivers (JHP, done)
- Power up/down scripts (LAT00x/LAT01x) (ST)** Test bed/LAT vs small test stand instances
- Safe mode script (LAT08x) (JHP)
- File handling script (LAT04x) (JHP)
- Science data handling (RC, MEH, JJ, Eric Charles)
- VSC portion
- Packet sorting and reassembly
- Decompression
- LDF augmentation
- ASC handling
- LCI scripts (LAT30x, LAT31x, LAT40x, LAT41x, LAT50x, LAT51x) (LHM)
- LPA scripts (LAT22x) (LHM)
- Remaining scripts: LAT Performance and Operations test cases (all)
- Run number handling
- Location identifier
- Runs database
- E-logbook
- Insertion of run information from ScriptEngine
- Science data handler interface
- Analysis script interface
- Grouping of suite instigated runs
- Grouping of analysis runs with DAQ run
- Non-FSW configuration (JHP)
- Archivers
- VSC/SC location
- Serial numbers
- Opaque blocks
- Installers (PFK)
- LICOS
- FSW
- VSC
- E-logbook
- MOOT
- Shell scripts (launcher, etc.)** Launch RunControl (and other LATTE bits)
- Launch ScriptEngine (and other LICOS bits)
- Launch E-logbook
- LICOS release preparation** V&V
- LATTE release to resolve issues uncovered by running in Linux** Font issues
- Case sensitivity
- IP port reuse
- Multiple instances on one CPU
- Read-only issues for .cfg files
- Mobile racks
- LATTE demo
- E-logbook demo
- LICOS demo
- Installers
- Validation
- Documentation
- Machine IDs
- 2nd rack installation
- Create ODS-user account
- Create accounts for Sergio, Owen (needs root), Joanne, Kim, Tony W.
- Set up desktop of ODS-user
- Work out disk layout*** Ancillary, data, reports, etc.
- Stash files
- Multiple drives
- Training of John and Rodney to do installations
- John to update installation and CM procedures
- NRL certification work*** Set up machines
- Set up test(s)
- Provide instructions to NRL team
- Mobile workstations
- Mobile displays/keyboards/mice
- CVS
- Package for shell scripts (LICOS_etc?)
- Package for configuration files (LICOS_configs?)
- Package for scripts (LICOS_scripts?)
- Package for tools (LICOS_tools?)
- Suite handling** Automatically create suite summaries
- FastCOPY maintenance
- Usage with LATTE
- Archive file playback
- Thermal group support
- Telemetry Table GUI .cfg file for their needs
- .cfg file for environmental data transfer to NRL Windows machines
- Port thermal GUI used at Lockheed (Jana)
Jim's personal to-dos
- Alarm Handler
- Alert propogation up the chain (30 min)
- Disable individual alarms from GUI (3-4 hr)
- Disable groups from config file (2-3 hr, combined w/ above)
- Disable alarms from other scripts (4-6 hr, cvt protocol work)
- Email alerts (Req: email gateway. 1-3 hr)
- Text formatting (Lo priority)
- Full LAT alarm configuration (3-4 hr)
- Core LICOS
- FILE.deleteDirectory return status (20 min)
- File uploads to EPU (3-6 hr)
- FILE state machine checking in primary boot (2-4 hr)
- Trending DB purge cron job (3-6 hr)
- Strip Chart configurations (2-3 hr)
- Find out why FreeSpace is throwing an exception during export (1-2 hr)
- Runs db work with Lester (2-4 hr)
- Scripts
- Safemode script (LAT08x) & V&V doc (1-2 day)
-
- LAT04x changes from R. Baun:
- add csv files to export
- remove extraneous print statement (debug state)
- LAT04x changes from R. Baun:
Priorities for script completion (R. Baun):
- NB: Script definitions have changed somewhat since this list was created (11/18/05)
- NB: The definitions of the scripts is still in flux as of 3/1/06
1) LAT001/LAT002 - Power On
1) LAT011/LAT012 - Power Off
1) LAT041/LAT042 - Baseline Science Ops Config
1) LAT221 thru LAT226 - Science Ops Demo (to test Cu paths in cross-strap configurations)
2) LAT301/LAT302 - ACD CPT
2) LAT401/LAT402 - CAL CPT
2) LAT501/LAT502 - TKR CPT
3) LAT211/LAT212 - Timing Measure & Adjust
3) LAT071 - Energy Measurement Calibration
4) LAT031/LAT032 - EPS Performance
4) LAT131/LAT132 - SC/LAT Interface Functional
5) LAT021/LAT022 - Reinitialization
5) LAT061/LAT062 - SIU/EPU Hardware Functional
6) LAT151/LAT152 - Thermal Control (BLT version)
6) LAT161/LAT162 - Survival Heater Test (BLT version)
6) Cross-strap configurations for the tests in tiers 1, 3, 4, and 5.
6) LAT521 - Light Tight Test
6) LAT650 - T&DF False Triggers
6) LAT660 - T&DF Transport Errors
7) LAT081/LAT082 - Safe Modes
7) LAT121/LAT122 - Science Modes
8) LAT201/LAT202 - Science Performance Diagnostics
8) LAT231 thru LAT234 - GRB Handling
9) LAT311/LAT312 - ACD LPT (need for Pre-ship test)
9) LAT411/LAT412 - CAL LPT (need for Pre-ship test)
9) LAT411/LAT412 - TKR LPT (need for Pre-ship test)
Priority tier descriptions:
- The LAT must be powered on, off, and put in a state where science data can be taken before anything else.
- Detector Hw performance is of the next highest priority.
- Understanding the timing and interaction of the entire instrument is a high priority.
- These are higher risk (in my mind) hardware verification tests.
- Medium risk hardware verification tests.
- Low risk hardware verification tests.
- Hardware/Software interface tests.
- LAT Level demonstrations.
- Pre-ship tests (after Phase 2).