  • hsd-kcu eyescan software needs to be pushed
  • Julian will merge the eyediag and/or eyescan branches as needed
  • hsd jesd scan is in progress
  • XPM order need to clarify if there are one or two orders, and how many pm's does the photon side get?  We need 2 for mfx, 2 for txi plus spares.  Matt is asking Thuy for this info.
    • Update: Matt writes that we own the following hardware: "2 boards are ready, 2 are still being completed by Lupe.  We have 10 AMC cards (need 2 per carrier).  We have 2 passive timing fanouts and 2 network switches (one is in use elsewhere).  She lists 2 atca crates with no location - I think those are not yet acquired".
  • ATCA crate vendor still in-progress (need 2: mfx/txi)