This page attempts to block out the noticeable episodes of computing and their priority and need for resource availability.
Instrument Related - Pre Launch
What | When | Resource Uptime Needed |
---|---|---|
vibe/acoustic |
| |
TVAC | Aug-Sept (40 days) | up to 8 hr outages allowed |
Kennedy Ops |
|
|
ISOC testing - Pre-launch
What | When | Resource Uptime Needed |
---|---|---|
ETE3 | August 2007 (2 days) | uptime needed |
ETE4 | Oct 2007 (2 days) | uptime needed |
ETE5 |
| uptime needed |
ETE6 |
| uptime needed |
ISOC Ops Sim 1 | Oct 2007 (about 4 days) | uptime needed |
ISOC Ops Sim 2 | Dec 2007 (about 4 days) | uptime needed |
Flight Operations Post Launch
What | When | Resource Uptime Needed |
---|---|---|
First 2 weeks | Feb | "Guaranteed" up |
Next 6 weeks | Through to end March |
|
Routine Ops | April onwards | up to 8 hrs; max 48 hrs |
Simulations
What | When | Resource Uptime Needed |
---|---|---|
Preparations for 1 year run | Several bursts of 1-3 farm-days, July-Aug | Advance notice for up to a few days' outage |
Backgrounds for 1 year run | 3 weeks in Sept | Advance notice for < 1 day outage |
1 year run | 3 weeks in Oct | Advance notice for < 1 day outage |
ISOC test datasets | More bursts of 1-3 farm days, July-Sept | Advance notice for up to a few days' outage |
Post ISOC test/pre launch datasets | end Oct - Jan | Advance notice for up to a few days' outage |
|
|
|
|
|
|