Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • How many hours each account spent on project tasks (up to the total amount of hours they charged in the previous month)
  • Their progress on said task (in % complete) and inputting that into the correct row of the budget sheet
  • Then you compare that the WBS actuals and figure why there are differences (assuming there are any)
  • If the costs are not in any of the rows then add a row under 'unplanned activities' for the program manager to address
  • in the tracking file of the project we copy paste the current row onto the correct month

...