This field contains the incoming Total Budgeted Cost from the project file.
This field contains the incoming actual cost from the project file. This number needs to match the "Total Actuals From Finance" field.
This field contains computes the incoming remaining funds from in the project fileproject.
This field contains the incoming earned value from the project file.
...
This field contains the cost variance (how over budget is the project) value from the project filecomputation.
This is the cost performance index. CPI = Earned Value / Actual Cost
...
This is the schedule performance index. SPI = Earned Value / Planned Earned Value
This field contains the ration between Total Actuals From Finance and Actual Cost. This value should always be between 0.95 and 1.05 for properly tracked projects.
This field contains the tracking risk score based upon the value in the "Reporting Index" field. This is generated automatically based upon a formula and may be overridden on each month's status line with pre-approval of the Division Director.
This field contains the budget risk score based upon the value in the "CPI" field. This is generated automatically based upon a formula and may be overridden on each month's status line with pre-approval of the Division Director.
...