Comment: Panel holes were mentioned twice

...

  • Check permanent and variable filtering (flippies) for cameras in laser room – Laser cameras and alignment references
  • Check permanent and variable filtering (flippies) for cameras in tunnel – Laser cameras and alignment references
  • Determine safe set of motor positions for everything in the PB – Motor positions
  • Fix hole size for laser shutter enclosures
  • Write up procedure/check list
  • Find an reliable energy controlling method:
    1. Use wave plate + thin film polarizatior. This will have to test the minimum achievable energy using such combination (ideally <10mJ), and test the damage threshold of the polarizor
    2. Measure change in collimation as function of pump delay (SAGA attenuation, WP+thin film polariser?)? – or come up with strategy to enable slow ramp up of energy without RP attenuator
  • Figure out how to send beam at lower repetition rate
  • Fix the panels for laser shutter - a high power beam with diffraction profile may cause some harzard to the gratings
  • Check with Spencer on how to use the DAQ for laser-only operation, e.g. to save CompNear/Far, PBNear/Far and probe cameras simultaneously, scan waveplate etc.

...