Schedule:

  • FEE Commissioning: December 1st?
  • TMO first light (easier): Jan. 24, 2023
    • KPP:  MUST have ability to read out the piranha line camera on FZP and ability to read out two HSD channels on MBES but only if GMD/XGMD measurement doesn't work; could also be an opal
  • RIX first light (harder): ~March 2023
  • LCLS-II KPP test with soft-x-ray in the hxr line in txi (March/April)  they may need a wave8 or a hsd or a (controls?) camera to see the signal? (phil heimann is coordinating) - air attenuation tests; 3 keV
  • KPP measurements on hard x-ray line in the FEE (may only need power meter, or slow signal that gets fed back to ACR)

General to do

  • recabling to srcf (cpo+ric+others)
    • use data volume to each node to figure out cabling
    • what should go through the bos? exclude opals? 
    • what should use MPO (Nov 1 checkpoint for laser locker/XPP; switch on Nov 16; revert by Nov 18 if unsuccessful) including BLD, IOC, FIM, XTCAV, Mono Enc TPR (we can switch daq timing independently of controls timing)
    • IOC depends on Kukhee's software
    • high rate BLD depends on Dawood's software
    • Jeremy Mock writes about XTCAV: "Hi Chris, we can test the camera triggering soon, probably in October some time.  However, I think XTCAV proper (the klystron) won't run on lcls2 timing until sometime next year.  I think I heard maybe February...?".  Pat Krejick is coordinating the change.
  • 33kHz BLD: ebeam, gmd, test asap. waiting for software development (depends on Dawood)
    • test reception of 33kHz gmd without beam ASAP working with Marcio
  • commission s3df
  • migrate ctl nodes (move hsd processes onto daq-tmo-hsd-01 (Ric), but not mono encoder)
  • commission xpm0 in 208 (weaver)
  • (would be nice) xtcav "nice" for acr? how do we share between tmo/rix: need bos-switchable timing?
  • (would be nice) test psana2 live mode again (mona)
  • training for scientists (e.g. on timing system and sequences) (matt)
    • check we have psana2 detector interface for "sequence bits" (Matt thinks we have this: 272 bits)
  • timing in all detectors

s3df to-do

  • (done) psana1 (mikhail, valerio) psana2 (mikhail, mona, valerio)
  • (done) smalldata code (silke, vincent)
    • will ask wilko to move some psana1 data over
    • need path to install packages
    • done by early february?
  • movers (wilko)
    • few days of work.  still needs some work on feb. 15
  • need some kafka work for movers and elog (wilko)
    • should be ready for early february.  still needs some work on feb. 15
  • need some data management machines and irods (replaced by rucio in a few months) integration (wilko)
    • still needs some work on feb. 15
  • data storage (omar)?
    • backend spinning-disk (aka "s3") 10's of PB done early january
    • will get 1.5PB of flash free space by third of week of january
    • serious issue (has been worked-around by using "/home" and relaxing ACLs for FFB): no extended ACL's since mounted via nfs.  need multi-cluster feature? (expected in april?) or fully functional nfs?
      • could workaround by making group the expt group, but then access via ps-data (e.g. silke) wouldn't work
  • mon-node mount of calibdir (under /sdf/data/lcls) via weka-nfs (IT)  (done)
    • will try third week of january
  • ARP (murali, wilko)
    • should be straightforward copy of what we currently have. confirm with murali. (still needs work on feb. 15)
  • jupyter/ondemand (wilko, riccardo) (done)
    • could provide yee with default kernels (cpo will contact yee/wilko)
    • can run in batch queues (charged) and interactive nodes (free!!!)
  • (done) LCLS group permissions syncing (wilko)
  • finalize high-priority analysis mechanism (reservations, we believe)
    • need coact (like iris at nersc) stuff from murali available by beginning of february
      • need management accounts to create per-account CPU allocations with coact.  still needs work on feb. 15
    • will also coact to enable their s3df account
  • enable user access to s3df (IT)

tmo to-do

Equipment list:

  • magnetic bottle (few hsd channels)
  • 2 opals (fzp, atm).  atm alignment could be in controls?  eventually cvmi opal in run 22.
  • 2 piranha (atm, fzp)
  • bld (ebeam, gmd, xgmd)

...

Code Block
[camera,   need by date,   retire date]
[cvmi_opal_1, oct 27, nov 19] - retire date is negotiable, (maybe needs to be earlier?)
[cvmi_opal_2, oct 27, nov 19] - retire date is negotiable, (maybe needs to be earlier?)
[atm_opal,       oct 27, possibly run 22]
[fzp_opal,        oct 27, possibly run 22]
[atm_pirhana, oct 27, not planned]
[fzp_pirhana,  oct 27, not planned]


rix to-do

Equipment list:

  • 3 andor newton
  • 3 wave8
  • 1 piranha (atm)
  • 1 opal (atm)
  • bld (ebeam, gmd, xgmd)
  • high-rate interpolated mono encoder (caf)
    • what is the right way to use that encoder (absolute or relative for the motor?)
    • relative encoder is still with vendor; early next year arrival at SLAC; try to integrate and read out at higher rates (work with Zach)
  • EXS Manta (coordinate with controls for timing/sequencing)
  • 1 channel HSD for coarse timing (rate? 1 kHz ok if we can see the whole waveform)

...