Building of EUDAQ 1.7 release continues. Challenge now is installing extern/libusb without internet and system privilege. Settled the new ESTB user 116PRA training session to be Tuesday 11am at Bldg 28-141. Carsten warned that Tuesday May/29 morning will be preoccupied with dismantle of previous experiment and moving concrete shielding.which may use up all access keys. Our access to ESA may need to wait until at least Tuesday afternoon.   

May/29

10:00AM ESA on permitted access so that no longer needs controlled key access until we close the area for beam.

10:30AM Concrete removal for previous experiment is still on going. Looks like at least 2-3 hours before we can move in.

11:00AM T539 new comers training for 116PRA at Building 28-141. A separate session is schedule for the LBNL T545 gang on Thursday.