Day/Week | Dates | Activities |
---|---|---|
Monday | May/21 | Installation of EUDAQ 1.7. Last chance to test inside tunnel. |
Tuesday | May/22 | Caladium to be removed from tunnel due to invasive beam experiment before us. |
May/23-28 | Caladium parked inside ESA outside beamline but powered on and connected to allow continued new DUT software integration. | |
Tuesday | May/29 | Dismantle of previous experiment by EFACTest Facilities. Caladium reinstallation in beamline and DUT setup can start in ~afternoon. New user in person training 116PRA: 11:00am–12:00 noon, Building 28 Room 141 |
Wednesday | May/30 | Installation and integration. Potential first beam. |
May/31-Jun/5 | Formal run period | |
Tuesday | Jun/5 | Beam off at 9am |
...
Building of EUDAQ 1.7 release continues. Challenge now is installing extern/libusb without internet and system privilege. Settled the new ESTB user 116PRA training session to be Tuesday 11am at Bldg 28-141. Carsten warned that Tuesday May/29 morning will be preoccupied with dismantle of previous experiment and moving concrete shielding.which may use up all access keys. Our access to ESA may need to wait until at least Tuesday afternoon.