Tim gave us a presentation.https://confluence.slac.stanford.edu/display/hpsg/11.27.2017+EC+Meeting SVT_Upgrades_EC_1711.pdf

Delays in getting approval at SLAC and difficulties and delays in transferring money to Spain have resulted in project completion moving to January 2019.  Tim is close to approving the sensor order, which drives the timeline.

...