the batch ready by and tested by 9/15
Item/TaskSub-item/taskOwnerDatesComment
FEB
 
Ben  
 layout 

Done

 
 fabrication done 
 loading 8/2629 
 testing 2 boards 8/27-9/5 
 rest of FE boards fab and loaded 9/12 
 all FE boards tested 9/19 
L4-6 Half-module production Tim/Omar  
 apv25 loading done 
 hybrid & sensor QA done 
 half-module production incl. QA 9/5 
L1-3 Module assembly Tim/Sho  
 Modules for detector  9/5 
 Spares 9/5 
L4-6 Module assembly Tim/Sho  
 Modules for detector 9/12 
 Spares 9/12 
FEB support Richard  
 Machine slots in support box   
 Design pockets (need final FE board)   
 Fabrication and dry assembly 9/15 
Mechanical dry run assembly  Who?  
 w/o cabling and real FEBs (but FEB cold plate) 9/5 
     
Motion control system check Takashi  
 Test stages on vac box 9/5 
 Connect bottom U channel, set limits, calibrate 9/12conflict with survey?
 Connect top U channel, set limits, calibrate 9/12 
Survey  Tim/Sho overview and procedures needed
 L1-3 module survey 9/12 
 L4-6 module survey 9/12 
 U-channels survey 9/12Need mounted modules (see below).
 SVT full assembly survey 9/22-9/26 Coordinate with alignment group (see below)
Internal cabling Tim/Dave  
 Magnet wire signal transmission test done 
 Magnet wire high voltage test donePelle will do it.
 FEB mezzanine card layout done 
 FEB mezzanine card fabrication 9/5 
 Hybrid mezzanine card layout 9/5 
 Hybrid mezzanine card fabrication 9/5 
 L1-3 cross-over board design 9/12 
 L1-3 cross-over board layout 9/12 
 L1-3 cross-over board fabrication & assembly/checkout 9/12 
 LV mezzanine card layout   
 LV mezzanine card fabrication   
 

HV mezzanine card layout

   
 HV mezzanine card fabrication   
 pre-production bundle assembly 9/12 
 pre-production bundle test with FEB 9/19 
 production bundle assembly and test 10/6 critical path for full assembly (see below)
 FEB power bundle design (from flange) done 
 FEB power bundle assembly (from flange) 8/26Need cable length estimate. 2 days of shop work.
 FEB high voltage bundle design (from flange) done 
 FEB power bundle assembly (from flange) 8/26Need cable length estimate. 2 days of shop work.
 

FEB data bundle design (to flange)

   
 FEB data bundle assembly (to flange)   
External cabling & Power pelle  
 High voltage 8/222/3 bundles done. Waiting for more wire.
 Low voltage Done. 
 Fibers Done.Between flange and DAQ crate.
 PS checkout Done. 
 PS epics control 9/5Can control through backup interface until ready.
Power flange Pelle  
 Flange w/ board assembly 9/12One spare included.
 Testing with FEB and PS 9/12Need dummy connector on power. High voltage with banana plugs?
Signal flange Pelle  
 Board fabrication (5 boards) Done. 
 Board prepping 

Done.

 
 Board testing Done.Needs Ben for high-speed tests.
 Flange w/ board assembly 8/20-8/27Potting.
 Board fabrication (spares) 9/5 
 Board loading (spares) 9/5 
 Board testing (spares) 9/5Needs Ben for high-speed tests
Chiller and cooling system Marco9/12 
Target Clive/Marco  
 Design 9/5 
 Fabrication 9/19 
 Testing 9/26 
Wire frame holder Clive/Marco/Takashi  
 Design done 
 Fabrication 9/12Wire Stretching
 Testing 9/12 Mechanical dry run assembly
  Shawn   U-supports, FEB cold plate, stages 8/8 
  Define cable lengths for power and HV bundles  8/8 Motion control system check
Final SVT Assembly Takashi8/15 Mechanical assembly  
   Mount modules in U-channels 9/22 
 Dress modules in U-channels with cabling 9/26 cabling not ready?
 Assemble FEBs on cooling plate and dress with cables 10/17 cables are ready 10/6  Need 11 days?
 Full SVT assembly including stages 10/22 Ready for full system
ATCA/RCE Platform hardware Ryan/Pelle  
 RTM layout doneAfter testing trigger interface at JLab.
 RTM fabrication & loading done 
 RTM checkout 9/5 
SVT DAQ commissioning Ryan/Ben  
 Commissioning of RCE platform with multiple FEBs and hybrids 9/8-9/19Need: flanges, FEBs and hybrids. Can be done with spares if interfering with assembly.
 Commissioning/testing of full RCE platform 10/20Use all final hardware with increasing number of FEBs/modules.
Shipping Pelle/Matt  
 Box design 8/29Nr of boxes, isolator requirements for transport of delicate modules
 Procurement/fabrication 9/19 
 Assembly 10/3