- Neutrons shielding for front end boards - update: Takashi 2014-08-04Neutron.pptx

 

- Fall beamline commissioning work in October and November: plans, people needed, etc. - Stepan 

no report 

Beam line experts for 2014 run:

Stepan 5, Francois 4, Takashi – 1. Others may be certified for the 2015 data taking runs.

Oct 10-17                FX Girod

Oct  18-25               Stepan Stepanyan

Oct 26- Nov 1         Stepan Stepanyan

Nov 2-Nov 9           FX Girod

Nov 9-Nov 16         FX Girod

Nov 17- Nov 22      Stepan Stepanyan

 

Nov 22-29               Stepan Stepanyan

Nov 30-Dec 6         Stepan Stepanyan

Dec 7-Dec 14         FX Girod

Dec 15-Dec 22       Takashi Maruyama

Note, circumstances may require the schedule be revised in the future.

 