  • Hovanes and Krister met with Dave Butler from Hall D and described him the requirements for SVT interlocks
  • Dave gave us his recommendations for the PLC modules as well as quotes from the local (for JLab) PLC dealer.
  • If no objections are received by Friday morning, Hovanes will forward these quotes to Marco for procurement.
  • Stepan asked if the flow meter for the SVT interlocks will be speced and procured by JLab or SLAC groups. Hovanes' understanding is that Marco will take care of specifying the flow meter and either JLab or SLAC can buy it. Pelle will double check this to determine who does this.
  • Hovanes contacted JLab PSS people regarding having an FSD input to the SVT interlocks. PSS group will help us to set it up.

...