During ramp up


  • Attenuate laser and gradually ramp up
  • Check light levels on all cameras, look out for abnormalities that indicate damage
  • Check vacuum levels as beam is dumped on compressor block
  • Check vacuum levels as beam is dumped on laser beam dump in PB
  • Check for damage, signs of ablation etc. around compressor block and laser beam dump in PB
  • Check if scaling on laser diagnostics matches expected energy scaling (for on-shot energy measurement)

...

  • Laser aligned upstairs, through transport and to diagnostics
  • Check cameras for beam clips
  • Motors in safe positions
  • If probe only work, insert compressor beam block
  • Laser flippers for filtering in, confirm on cameras, check for any clips
  • Block laser
  • Block CW diode
  • Attenuate laser
  • Remove RP attenuator 
  • Unblock laser
  • Slowly ramp up while observing cameras and vacuum levels
  • Full power! 

...