- For the days of April 3-18 RF and magnets will be running old software, BPMs & BLENs on new software, BLD in production testing.
- Just got agreement from Rick Iverson that the RF and Magnets / matlab feedbacks / other feedback related commissioning will occur the week of April 19-23.
- we will have the day shift for each of these days. We must leave the machine in a good state at the end of each day for other work being done on the swing/owl shifts.
- RF and magnets must be controllable at the end of our day shifts.
- Debbie says the PAU can be turned off in the magnets, leaving them with the usual PV control, so we can try leaving the new software in.(test this early!)
- Charley and Kukhee need to make a plan to manage the switch configuration for this commissioning week.
...