Action Items

...

CategoryAction ItemAssigneeTimelineStatus
DocumentationReview all diagrams and
chassis
drawings.Bo
/
, Thi

Hardware Design

2024

Status
subtletrue
colourYellow
titleWIP

Hardware Design
Action ItemAssigneeTimelineStatus
Update HMC1119 Variable Attenuator PCB.ThiDecember 2023

Status
subtletrue
colourGreen
titleCOMPLETE

Hardware DesignBuild MO-LO Power Supply Chassis with +8V/+18V switching supplies.ThiApril
-May
2024

Status
subtletrue
colourRed
titlePENDING

Miscellaneous

...

Action ItemAssigneeTimelineStatus
Set up long-term test environment for HMC1119 Variable Attenuator testing.ThiApril 2024

Status
subtletrue
colourYellow
titleWIP

MiscellaneousReceive access to lcls-srv01.ThiApril 2024

Status
subtletrue
colourGreen
titleCOMPLETE

Procurement

...

Action Item
AssigneeTimelineStatus
Follow-up with Nate on procurement timeline.BoApril 2024

Status
subtletrue
colourYellow
titleWIP

Testing

...

Action ItemAssigneeTimelineStatus
HMC1119 Variable Attenuator long-term testing.ThiMay 2024

Status
subtletrue
colourRed
titlePENDING

TestingSet up the HE PRL system in the lab for PCB, PA and system integration.Bo and Thi2024

Status
subtletrue
colourRed
titlePENDING