05/23

Pre-Planning meeting

06/??
01

Protein model prototypes ordered Kickoff meeting

06/1105

Conference validation done Protein model selected

06/15

Booth design complete

07/02

Conference validation request submitted

18

Protein model prototypes ready

06/21

Protein model selected

06/27

All Hands meeting

07/09

3D printing of protein model starts

07/16

Start preparing DOE conference approval request

08/01*

Freeman order process begins

08/01

SCinet connection order opens

08/03

Booth design complete

08/10

Giveaways Handouts decided

08/15

3D printing of protein model starts

08/28

Booth theme decided

08/1031

Artwork for handouts shirts ready

08/2231

Dell shirts Additional frame elements ordered

0809/25

Booth logo design ready

08/27*

SCinet connection order opens

04

Print material ordered

09/04

Additional display elements ordered

09/05

Artwork for giveaways

08/31

Artwork for shirts ready

09/0307

Dell shirts Giveaways ordered

09/10

DOE conference approval request submitted

09/14*

Entry in Exhibitor Directory  Listing

0809/14

Handouts ordered Booth logo design ready

09/1421

Protein model Hanging sign printed

09/25*28

Deadline for SCinet connection order to avoid $1000 late fee

0910/3001

Additional frame elements  delivered

10/01*18

Advance rate deadline for electrical connections

10/01

Shipping crates ordered

10/07

Giveaways  Handouts  delivered

10/0108

Display wall content ready

10/08

Protein model printed Shipping crates ordered

10/10

Deadline for hotel cancellation without penalty

10/15

3D content ready

10/15

Shipping list completed

10/15

Protein model assembled

10/18

Discount Deadline to Order all Freeman Labor, Furnishings & Services

10/17* 19

Deadline for early registration

10/19

Shipping crates delivered

10/22

Display  pre-assembly completed

10/25*30

Posters printed Discount Deadline to Order all Freeman Labor, Furnishings & Services

10/30

Packing hardware starts

11/02

Packing hardware complete

11/05

Hardware ready to be shipped

11/08

Direct-to-site shipment arrives

11/08

Exhibits Installation    8 am – 5 pm

11/09

Exhibits Installation    8 am – 5 pm

11/10

Exhibits Installation    8 am – 5 pm

11/11

Exhibits Installation    8 am – 5 pm

11/12

Booth Cleanup            8 am – 4 pm

11/12

Exhibition Opening Gala 7 - 9 pm

11/13

Exhibition Open          10am – 6 pm

11/14

Exhibition Open          10am – 6 pm

11/15

Exhibition Open          10am – 3 pm

11/15

Exhibits Dismantling  3pm – midnight

11/16

Exhibits Dismantling  8am – noon

11/16

Booth hardware shipped back to SLAC

12/17

Booth hardware distributed/recycled/disposed

*

Approximate date based on SC2011

...