QA Studies 2013

SVT DAQ QA Studies 2013

Goal: Improve our understanding of the SVT DAQ and in particular study issues identified during the QA and operation of the Test Run.

The studies are split up into testing that can be performed using the development board and the full DAQ.

Development Board Testing 2013

...

Establish baseline performance

...

Redo QA tasks to establish baseline understanding of the development board equipment.

Tasks:

  • Leakage current and noise vs bias
  • At nominal bias (80V)
  • Noise, pedestal, gain,t0

...

Shaping time to 35ns

...

Redo all calibration from QA: noise, pedestal, gain, t0, with Tp=35ns

...

Understand absolute scale

...

GUI indicates 18125e- being injected rather than 25000e- (nominal)
Use source to calibrate this absolute scale

...

Double peak structure in pedestal distributions

...

Are these caused by reflections or pedestal shifting

...

Operational stability over time

...

Run calibrations/pedestals for same chip/sensor over hours/days

Tasks:

...

Operation at cold temperature

...

Establish experience and understand APV25 behavior at lower temperatures. We'd like to understand and benchmark performance for a few different temperatures.

Temperature operating points (in C):

7

0

-5

-10

-15

Tasks:

  • Setup hardware needed for tests and identify halfmodule to be used
  • Establish APV25 operational settings for all temperatures
  • Study leakage current,power consumption, noise, gain, t0 resolution vs temperature

...

Edge channel noise on APV25

...

Tasks:

...

Run at clock frequency of about 50MHz

...

Tasks:

Full Test Run SVT  Testing 2013

 TBF

Documentation