Search/Navigation:
Related:
SLAC/EPP
/HPS Public
Jefferson Lab/Hall B
/HPS Run Wiki
S30XL-LESA/LDMX
...
- Neutrons shielding for front end boards - update: Takashi 2014-08-04Neutron.pptx
- Fall beamline commissioning work in October and November: plans, people needed, etc. - Stepan
no report
Beam line experts for 2014 run:
Stepan 5, Francois 4, Takashi – 1. Others may be certified for the 2015 data taking runs.
Oct 10-17 FX Girod
Oct 18-25 Stepan Stepanyan
Oct 26- Nov 1 Stepan Stepanyan
Nov 2-Nov 9 FX Girod
Nov 9-Nov 16 FX Girod
Nov 17- Nov 22 Stepan Stepanyan
Nov 22-29 Stepan Stepanyan
Nov 30-Dec 6 Stepan Stepanyan
Dec 7-Dec 14 FX Girod
Dec 15-Dec 22 Takashi Maruyama
Note, circumstances may require the schedule be revised in the future.
- Other?
Ken