Agenda
1) Update on beam line installation - François
2) Talks and speakers for beamline session at the collaboration meeting in June. 
Suggested talks speakers:
a) Beamline overview, budget, schedule, beamline commissioning documents and preparation for beamline issues at readiness review 
             Ken - 20 min                                                        
b) Hall B work: show and tell progress, schedule/milestones for completion.          
 Francois - 40 min
c) MPS/FSD systems
 Accelerator Operation Person – 15 min
d) Silicon detector stepping motor test.                                                              
 Takashi - 15min
Discussion in meeting and post-meeting recommended changing the agenda:

Agenda for the Collaboration Meeting (21 May 2014)
a) Beamline overview, budget, schedule, beamline commissioning documents and preparation for beamline issues at readiness review
Ken - 15+5 min
b) Hall B work: show and tell progress, schedule/milestones for completion.
Francois - 30+5 min
c) MPS/FSD systems
Accelerator Operation Person - 15+5 min
d) Radiation safety in Hall B and Alcove
Accelerator Operation Person - 15+5 min
e) Silicon detector stepping motor test.
Takashi - 15+5 min
f) Targets and design of target the ladder.
Speaker - 15+5 min
Total will be 2 hours.

3) HPS PC & HARP near HPS
a) Do we need the wire at the bottom of the PC?
·         We have to scan to find the edges of the tungsten slit anyway seeing the rise in signal from the beam tails as we move up and down.
·         We will know the center of the slits well enough from survey to allow positioning of 3mm slit so the beam passes through the slit.
·         We will need physical STOP/switch on stepping motor for reference.
·         Do we use ECal signals during scan to find center of slit?
b) Do we need the thin gold foil on the PC if there is one on the HARP? If we have the thin gold foil on the PC do we need a 3-mm slit before the gold foil to protect stuff downstream?
c) Edit operation manual for HARP to include gold foil?
HPS PC already designed with gold target and wire (see attachments).
4) Operation Manuals for HPS PC, HPS primary target and SVT movement (stepping motors). Takashi
 see attached talk by Takashi CollimatorManual.docx
5) Feedback to Stepan on Beam Operation Manual. The current beamline manual can be found at -

http://clasweb.jlab.org/shift/

...