New CSC Readout meetings during LS1 (including daily M6 prep)
- CS CSC Readout at M6 milestone run week , Oct/12-17, 2014
- CSC Readout at M5 milestone run week , Sep/8-12, 2014
- CSC Readout Commissioning week, Sep/1-7, 2014 (C3)
- CSC Readout Commissioning Week July 2014 (C2)
- CSC Readout Commissioning Week June 2014 (C1)
...
Date | Time | Run | E-log | Description |
---|---|---|---|---|
26/4/11 | 00:30 | 188242 | CSC link lock failed for CSC EC sectors 2,12 in run 188242 | |
23/4/11 | 12:08 |
| Replaced SPU B0 in ROD slot A06: fixes data integrity for Sector A02 Layer 1 | |
21/4/11 | 21:03 | 180124 | CSC related DAQ (monitoring) issues (CSC ADC time spikes and fit fail flag not propagating upwards ?) | |
20/4/11 | 18:41 |
| high rate test of CSC DPU code modification | |
18/4/11 | 12:41 |
| Change in OKS database (CSC main controlled moved from private machine to online machine) | |
13/4/11 | 19:08 |
| CSC high rate test (busy 4.5% @ 75Khz after initial confusion of a hot channel) | |
5/4/11 | 17:18 | 178992 | CSC errors during run 178992 | |
1/4/11 | 7:59 |
| OHP (large fraction of bad data - due to A01-02 losing HV) |
...