    • LAT04x changes from R. Baun:
      • add csv files to export
      • remove extraneous print statement (debug state)

...

Priorities for script completion (R. Baun):

  • NB: Script definitions have changed somewhat since this list was created (11/18/05)
  • NB: The definitions of the scripts is still in flux as of 3/1/06

1) LAT001/LAT002 - Power On
1) LAT011/LAT012 - Power Off
1) LAT041/LAT042 - Baseline Science Ops Config
2) LAT301/LAT302 - ACD CPT
2) LAT401/LAT402 - CAL CPT
2) LAT501/LAT502 - TKR CPT
3) LAT211/LAT212 - Timing Measure & Adjust
3) LAT071 - Energy Measurement Calibration
4) LAT031/LAT032 - EPS Performance
4) LAT131/LAT132 - SC/LAT Interface Functional
5) LAT021/LAT022 - Reinitialization
5) LAT061/LAT062 - SIU/EPU Hardware Functional
6) LAT151/LAT152 - Thermal Control (BLT version)
6) LAT161/LAT162 - Survival Heater Test (BLT version)
6) LAT221 thru LAT226 - Science Ops Demo (to test Cu paths in cross-strap configurations)
6) Cross-strap configurations for the tests in tiers 1, 3, 4, and 5.
6) LAT521 - Light Tight Test
6) LAT650 - T&DF False Triggers
6) LAT660 - T&DF Transport Errors
7) LAT081/LAT082 - Safe Modes
7) LAT121/LAT122 - Science Modes
8) LAT201/LAT202 - Science Performance Diagnostics
8) LAT231 thru LAT234 - GRB Handling
9) LAT311/LAT312 - ACD LPT (need for Pre-ship test)
9) LAT411/LAT412 - CAL LPT (need for Pre-ship test)
9) LAT411/LAT412 - TKR LPT (need for Pre-ship test)

Priority tier descriptions:

  1. The LAT must be powered on, off, and put in a state where science data can be taken before anything else.
  2. Detector Hw performance is of the next highest priority.
  3. Understanding the timing and interaction of the entire instrument is a high priority.
  4. These are higher risk (in my mind) hardware verification tests.
  5. Medium risk hardware verification tests.
  6. Low risk hardware verification tests.
  7. Hardware/Software interface tests.
  8. LAT Level demonstrations.
  9. Pre-ship tests (after Phase 2).