  • With the move to the new host Faisal had to get a new cookie to allow scriptroute to run scripts on the PlanetLab infrastructure. Still needs testing.
  • Get the MatLab license at SEECS and put up a CGB server using it. Do not have license for MatLab will do on own machines to test and will migrate when have license. Zafar will contact Arshad and Ali. Basically the client will call the reflector with the target. The reflector will return the landmarks and RTTs. The client will then call the CBG/MatLab server with the relevant RTTs, lat/longs etc. * Bilal has read the TULIP architecture. He has a moderate understanding of how it works. He is modifying CBG code. Now it is ready for integration with TULIP. I sent the reflector/eventhandler, tulip-viz.cgi, & Faisal sent the Java code to Zafar. A student was given a task. Zafar . - PROGRESS? needs to answer where we are, and the progress. Adnan will get back to us ibn a day or so to tell progress. There will be exams in the coming week, so progress may be stalled for a while. May be an issue with the MatLab

PerfSONAR

Problems were fixed. NTP servers were causing considerable clock delay. Added close-by Stratum 1 NTP servers to solve the problem. Nodes were updated to PerfSONAR version 3.2 (Fedora distro). Nodes however are offline since they were disrupting normal traffic. We are waiting for 10 Mbps dedicated connection to switch the nodes back on.

  1. Faisal is working with Yee.  
    1. Arrows for tracerouts being implemented by Faisal.
    2. Working with Yee to get Lat long of perfSONAR host corrected.
  2. Zafar - deploy PerfSONAR nodes at SEECS. Second step is to find whether the same can be done at HEC on PERN's network. It is working, congratulations!
  3. Internet2 Joint Techs meeting at the end of Jan. Can Pak PerfSONAR nodes be up by then?

...

  1. SVN for paper, Umar has set it up and it is working. Umar will send out the accounts. Not critical at the moment.
  2. Umar will take as the main/first author of the paper. Ali Khayam has put together an introduction
    identifying the main points. Umar will send in the first draft and put together with feedback from Ali. Umar hopes to be done by Mid December. Umar is currently overwhelmed. Zero progress 11/10/2011. Umar has to submit a camera ready copy in the next couple of days.
  3. Adnan is also interested in working on the paper and will talk to Umar.
  4. Umar sent draft to Adnan. Umar will be in Pakistan later this month and will get together with Adnan. Fida will be available after December 16th.
  5. Fida will send review comment to Adnan
  6. Meeting between Adnan, Umar, Khayam this coming Tuesday then Adnan will start start to work on re-writing the paperAli Khayam did not come to pass due to Adnan being sick. It is believed we need a re-write, the technical details are OK. Adnan will get to more rigorously.

AOB

Future meeting time - Les

...