Switch | IOCs for Feedback |
---|---|
swh-in20-nw02 | in20-bp01, in20-bp02, in20-rf01 |
swh-li21-nw01 | li21-bp01*, li21-bp02, li21-bl01* * |
swh-li24-nw01 | li24-bp01, li24-bp02, li24-rf01, li24-bl01 |
swh-b136-nw01 | bsy0-bp01 |
swh-b106-nw01 | bsy0-bp02 |
swh-b105-nw01 | ltu0-bp01, ltu1-bp01, ltu0-mg01? |
swh-b911-nw01 | ltu1-bp02, ltu1-mg01? |
swh-b912-nw01 | ltu1-bp03, ltu1-mg02? |
swh-b913-nw01 | ltu1-bp04, und1-bp01, und1-bp02 |
swh-b921-nw01 | und1-bp03, und1-bp04, dmp1-bp01 |
**- we may will install this new switch swh-li21-nw01 may be installed, move these iocs from swh-in20-nw02 to this switch
...
- Terri to make schedule for Network installation and test during downtime, with input from Sonya, Kristi, Kukhee, Sheng
- Terri to add Controller IOC installation, with input from Ernest
- Sonya, Till - detailed plan for BPM check-out after April start-up.
- Sheng - develop a plan for monitoring status of this BLD version 2 'concentrator' processor
- Kristi - which two magnet IOCs control the 4 new correctors?