MD Item | Procedure Link | Machine Time (shifts) | Responsible Party | Prerequisites | Notes | Completed |
---|---|---|---|---|---|---|
S20 BBA | Oct 13, 2022 | 2 | Yocky | x | ||
S20 matching studies/emittance in S20 | Sep 29, 2022 | 1 | White | Good pencil beam config, S20 Quad BBA, S20 launch feedback | x | |
2nC running/instability investigation | 2 | Loney | FJD interested | x | ||
Pencil beam config | Oct 13, 2022 | Alsberg | x | |||
Learning data for MDL FF / Track hardware issues | Oct 6, 2022 | Alsberg | ? | |||
Linac BBA | BBA Shift Plan | Loney | x | |||
Toroid ringing investigation | Sep 1, 2022 | Alsberg | ? | |||
DC magnet stability | Sep 29, 2022 | Parker | x | |||
Linac wakefield bump tuning exploration | Yocky | ? | ||||
Commissioning Laser Heater | Yocky* | Laser Heater Commissioning Task List | x | |||
7-hole Cathode Alignment Procedure | <1 | Loney | x | |||
3 nC Setup | 1-hour | Loney,Kalsi | Good Starting point at current charge configuration |
Link to FACET-II Global Planning Airtable
...