This field contains the incoming remaining funds from the project file.
This field contains the incoming earned value from the project file.
This field contains the incoming planned earned value from the project file.
This field contains the cost variance (how over budget is the project) value from the project file.
...
This field contains is the cost variance value, with contingency applied, from the project file. performance index. CPI = Earned Value / Actual Cost
This field contains the duration variance (how late is the project) value from the project file.
This is the schedule performance index. SPI = Earned Value / Planned Earned Value
This field contains the difference between the actuals total amount and the reported cost from the project file. This value must be as close to zero as possible.
...