- Before turning anything off, disable the IOCs running on the server in the mobile rack.
- Open
iocmanager
and sort by the "Host" column to list the IOC processes running on the rack's server.
- Move your attention to the "State" column, and for each IOC select "Off" in its respective cell.
- Navigate to the "Configuration" dropdown on the top left and click "Apply". This will only work if your UNIX account has CXI iocmanager privileges. You will be prompted to enter your username and password! A pop-up window appear somewhere inconvenient and ask you to confirm your actions
- .
- Confirm your actions
- ..
- Open
- Powering down the rack should be carried out in the following steps:
- Manually power down each chassis using its front or real panel power button if it has one.
- Switch off the surge protectors on the rear side
Setting Up the Mobile Racks:
...