  • Move Caladium into beamline and try dummy runs. 
  • Drill holes on top plate of the back stage and prepare L anchor on Bosch frame to get ready for mounting the LBNL telescope
  • Mount Carsten's silicon sensor on mini stage onto the back stage   
  • Fix focus of two AXIS web cams (13,14). 
  • Check EPICS remote control of PSUs and possibly add some channels.
  • Exercise backstage XY drive to map out the adjustable range
  • Locate all 3 unused DUT DAQ Ethernet lines and test+tag them 
  • Locate additional beam trigger cable(s) and install NIM fanout and NIM-TTL in case more separate triggers needed  

Afternoon:

  • LBNL party arrives ~1pm after fueled with dim sim
  • 2-3pm: half of LBNL party in 116PRA. Others+SLAC continue installation
  • 3:45pm ESTB orientation (AD106 training) for all new comers
  • Dry runs without beam

...