    1pm:  116PRA training at 28-141 for many LBNL crew arriving, while RD53A DUT setup can also start with Timon and others with training done already.

    3pm (tbc):  AD106 :  At the entrance of ESA, AD106 ESA orientation training for all new comers still need to take it.

 

Actual activities:

    12:30 Ke and Vallary are adjusting the X-Y position of the telescope to make sure the beam is at the center for all telescope planes.