- Extend Corner raft/CCS ICD to clarify details above (1 week – manager)
- Extend CCS/OCS ICD (LSE-71) to include above functionality (1 week – manager)
- Perform tests to confirm required latency for delivery of messages from "Guider Centroid Finding" to TCS. (Assuming that testing the DAQ->"Guider Centroid Finding" latency/throughput is a Corner Raft/DAQ responsibility).
- Include simulated guider functionality in early CCS/OCS pathfinder exercises (2 weeks software engineer)
- Develop and Test Guider HCU (6 weeks software engineer)
- CCS support for additional tests of complete guider system during I&T, Pathfinder, ComCam and commissioning (4 weeks software engineer)
...