FEB testing update
- DAQ development update
- DAQ mapping (Omar)
- Board status
- RTM: out for loading
- FEB LV mezzanine
- Signal flange boards (spares): in today being sent our for loading this afternoon
- Cross-over board
- Internal cable update
- 2nd FEB support plate for testing >2 FEBs, do we need it?
- Budget review