Item/Task | Sub-item/task | Owner | Dates | Comment | |||
---|---|---|---|---|---|---|---|
FEB | Ben | ||||||
layout | done | ||||||
fabrication | done | ||||||
loading | 9/3 | Received 8/29 | |||||
testing 2 boards | 9/12 | ||||||
rest of FE boards fab and loaded | 9/19 | ||||||
all FE boards tested | 9/26 | ||||||
L4-6 Half-module production | Tim/Omar | ||||||
apv25 loading | done | ||||||
hybrid & sensor QA | done | ||||||
half-module production incl. QA | 9/5 | two modules to go on 9/2 | |||||
L1-3 Module assembly | Tim/Sho | ||||||
Modules for detector | 9/12 | ||||||
Spares | 9/12 | ||||||
L4-6 Module assembly | Tim/Sho | ||||||
Modules for detector | 9/19 | ||||||
Spares | 9/19 | ||||||
FEB support | Richard | ||||||
Machine slots in support box | done | ||||||
Design pockets (need final FE board) | 9/12 | ||||||
Fabrication and dry assembly | 9/26 | ||||||
Mechanical dry run assembly | Who? | ||||||
w/o cabling and real FEBs (but FEB cold plate) | 9/5 | first stage mech progressing well | |||||
Motion control system check | Takashi/John | ||||||
Test stages on vac box | 9/5 | Work with Matt on details | |||||
Connect bottom U channel, set limits, calibrate | 9/12 | ||||||
Connect top U channel, set limits, calibrate | 9/12 | ||||||
Survey | Tim/Sho | overview and procedures needed | |||||
L1-3 module survey | 9/19 | ||||||
L4-6 module survey | 919 | ||||||
U-channels survey | 9/26 | Need mounted modules (see below). | |||||
SVT full assembly survey | Do after final assembly and checkout | ||||||
Internal cabling | Tim/Dave | Critical Path–Push Hard | |||||
Magnet wire signal transmission test | done | ||||||
Magnet wire high voltage test | done | ||||||
FEB mezzanine card layout | done | ||||||
FEB mezzanine card fabrication | 9/12 | ||||||
Hybrid mezzanine card layout | done | ||||||
Hybrid mezzanine card fabrication | 9/12 | ||||||
L1-3 cross-over board design | 9/5 | ||||||
L1-3 cross-over board layout | 9/12 | ||||||
L1-3 cross-over board fabrication & assembly/checkout | 9/19 | Push for 3 day turnaround. | |||||
LV mezzanine card layout | 9/5 | ||||||
LV mezzanine card fabrication | 9/12 | ||||||
HV mezzanine card layout | done | ||||||
HV mezzanine card fabrication | done | ||||||
Cable to LV (patch to FEB) | 9/19 | Ben to get quote on connect SOON | |||||
Cable to HV (patch to FEB) | 9/19 | ||||||
prototype hybrid-FEB bundle assembly | 9/19 | Needs cards back and FEB | |||||
prototype cross over-FEB bundle assembly | 9/26 | Needs cross over board | |||||
prototype bundle tests with FEB | 9/26 | ||||||
production bundle assembly and test | 10/6 | critical path for full assembly (see below) | |||||
FEB power bundle design (flange/patch) | done | ||||||
FEB power bundle assembly (flange/patch) | 9/5 | Need cable length estimate. 2 days of shop work. | |||||
FEB high voltage bundle design (flange/patch) | done | ||||||
FEB high voltage bundle assembly (flange/patch) | 9/5 | Need cable length estimate. 2 days of shop work. | |||||
FEB data cable design (flange/FEB) | done | ||||||
FEB data bundle assembly (flange/FEB) | 9/5 | ||||||
External cabling & Power | pelle | ||||||
High voltage | 9/12 | 2/3 bundles done. Waiting for more wire. | |||||
Low voltage | 9/19 | mod needed to present bundle | |||||
Fibers | Done. | Between flange and DAQ crate. | |||||
PS checkout | Done. | ||||||
PS epics control | 10/6 | Can control through backup interface until ready. | |||||
Power flange | Pelle | ||||||
Flange w/ board assembly | done | One spare included. | |||||
Testing with FEB and PS | 9/12 | Need dummy connector on power. High voltage with banana plugs? | |||||
Signal flange | Pelle | ||||||
Board fabrication (5 boards) | Done. | ||||||
Board prepping | Done. | ||||||
Board testing | Done. | Needs Ben for high-speed tests. | |||||
Flange w/ board assembly | done | ||||||
Board fabrication (spares) | 9/26 | Spares, no rush. | |||||
Board loading (spares) | 10/3 | ditto | |||||
Board testing (spares) | 10/10 | ditto | |||||
Chiller and cooling system | Marco | 9/12 | |||||
Target | Clive/Marco | ||||||
Design | 9/5 | ||||||
Fabrication | 9/19 | ||||||
Testing | 9/26 | ||||||
Wire frame holder | Clive/Marco/Takashi | ||||||
Design | done | ||||||
Fabrication | 9/12 | Wire Stretching | |||||
Testing | 9/12 | ||||||
Final SVT Assembly | |||||||
Mount modules in U-channels and survey | 9/26 | See survey above | |||||
Dress modules in U-channels with cabling | 10/10 | Use cables and cards completed 10/6 | |||||
Assemble FEBs on cooling plate and dress with cables | 10/10 | cables are ready 10/6 Need 11 days? | |||||
Full SVT assembly and cabling | 10/17 | Ready for full system testing | |||||
ATCA/RCE Platform hardware | Ryan/Pelle | ||||||
RTM layout | done | After testing trigger interface at JLab. | |||||
RTM fabrication & loading | done | ||||||
RTM checkout | 9/12 | ||||||
SVT DAQ commissioning | Ryan/Ben | ||||||
Commissioning of RCE platform with multiple FEBs and hybrids | 9/19 | Need: flanges, FEBs and hybrids. Can be done with spares if interfering with assembly. | Communication with single FEB using RCE platform | 10/3 | Use dev RTM if needed. | ||
Readout of multiple hybrids on single FEB using RCE platform | Use dev RTM if needed. | ||||||
Communication with two FEB using RCE platform | 10/10 | Use dev RTM if needed. | |||||
Readout of multiple hybrids on two FEB using RCE platform | 10/17 | Use dev RTM if needed. | |||||
| Readout of multiple (>2) FEB each with multiple hybrids. | 10/24 | Need HPS RTM. Preferrably with new internal cables and breakout board. | ||||
Test of "full" | Commissioning/testing of full RCE platform | 1011/137 | Use all final hardware with increasing number of FEBs/modules. | ||||
Shipping | Pelle/Matt/Bob | ||||||
SVT Box Design | 9/5 | ||||||
Procurement/fabrication SVT Boxes | Bob | 10/5 | |||||
Assemble SVT Boxes | Bob | 10/12 | |||||
Design Spares Boxes | 9/12 | ||||||
Order standard boxes | Marco | 9/26 | |||||
Pack Boxes | |||||||
Ship boxes |