Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Item/TaskSub-item/taskOwnerDatesComment
FEB
 
Ben  
 layout 

done

 
 fabrication done 
 loading 9/3Received 8/29
 testing 2 boards 9/12 
 rest of FE boards fab and loaded 9/19 
 all FE boards tested 9/26 
L4-6 Half-module production Tim/Omar  
 apv25 loading done 
 hybrid & sensor QA done 
 half-module production incl. QA 9/5two modules to go on 9/2
L1-3 Module assembly Tim/Sho  
 Modules for detector  9/12 
 Spares 9/12 
L4-6 Module assembly Tim/Sho  
 Modules for detector 9/19 
 Spares 9/19 
FEB support Richard  
 Machine slots in support box done 
 Design pockets (need final FE board) 9/12 
 Fabrication and dry assembly 9/26 
Mechanical dry run assembly Who?  
 w/o cabling and real FEBs (but FEB cold plate) 9/5first stage mech progressing well
     
Motion control system check Takashi/John  
 Test stages on vac box 9/5Work with Matt on details
 Connect bottom U channel, set limits, calibrate 9/12 
 Connect top U channel, set limits, calibrate 9/12 
Survey Tim/Sho overview and procedures needed
 L1-3 module survey 9/19 
 L4-6 module survey 919 
 U-channels survey 9/26Need mounted modules (see below).
 SVT full assembly survey  Do after final assembly and checkout
Internal cabling Tim/Dave Critical Path–Push Hard
 Magnet wire signal transmission test done 
 Magnet wire high voltage test done 
 FEB mezzanine card layout done 
 FEB mezzanine card fabrication 9/12 
 Hybrid mezzanine card layout done 
 Hybrid mezzanine card fabrication 9/12 
 L1-3 cross-over board design 9/5 
 L1-3 cross-over board layout 9/12 
 L1-3 cross-over board fabrication & assembly/checkout 9/19Push for 3 day turnaround.
 LV mezzanine card layout 9/5 
 LV mezzanine card fabrication 9/12 
 

HV mezzanine card layout

 done 
 HV mezzanine card fabrication done 
 Cable to LV (patch to FEB) 9/19Ben to get quote on connect SOON
 Cable to HV (patch to FEB) 9/19 
 prototype hybrid-FEB bundle assembly 9/19Needs cards back and FEB
 prototype cross over-FEB bundle assembly 9/26Needs cross over board
 prototype bundle tests with FEB 9/26 
 production bundle assembly and test 10/6critical path for full assembly (see below)
 FEB power bundle design (flange/patch) done 
 FEB power bundle assembly (flange/patch) 9/5Need cable length estimate. 2 days of shop work.
 FEB high voltage bundle design (flange/patch) done 
 FEB high voltage bundle assembly (flange/patch) 9/5Need cable length estimate. 2 days of shop work.
 

FEB data cable design (flange/FEB)

 done 
 FEB data bundle assembly (flange/FEB) 9/5 
External cabling & Power pelle  
 High voltage 9/122/3 bundles done. Waiting for more wire.
 Low voltage 9/19mod needed to present  bundle
 Fibers Done.Between flange and DAQ crate.
 PS checkout Done. 
 PS epics control 10/6Can control through backup interface until ready.
Power flange Pelle  
 Flange w/ board assembly doneOne spare included.
 Testing with FEB and PS 9/12Need dummy connector on power. High voltage with banana plugs?
Signal flange Pelle  
 Board fabrication (5 boards) Done. 
 Board prepping 

Done.

 
 Board testing Done.Needs Ben for high-speed tests.
 Flange w/ board assembly done 
 Board fabrication (spares) 9/26Spares, no rush.
 Board loading (spares) 10/3ditto
 Board testing (spares) 10/10ditto
Chiller and cooling system Marco9/12 
Target Clive/Marco  
 Design 9/5 
 Fabrication 9/19 
 Testing 9/26 
Wire frame holder Clive/Marco/Takashi  
 Design done 
 Fabrication 9/12Wire Stretching
 Testing 9/12 
Final SVT Assembly    
 Mount modules in U-channels and survey 9/26See survey above
 Dress modules in U-channels with cabling 10/10Use cables and cards completed 10/6
 Assemble FEBs on cooling plate and dress with cables 10/10cables are ready 10/6  Need 11 days?
 Full SVT assembly and cabling 10/17Ready for full system testing
ATCA/RCE Platform hardware Ryan/Pelle  
 RTM layout doneAfter testing trigger interface at JLab.
 RTM fabrication & loading done 
 RTM checkout 9/12 
SVT DAQ commissioning Ryan/Ben  
 Commissioning of RCE platform with multiple FEBs and hybrids
 9/19Need: flanges, FEBs and hybrids. Can be done with spares if interfering with assembly.Communication with single FEB using RCE platform 10/3Use dev RTM if needed.
 Readout of multiple hybrids on single FEB using RCE platform  Use dev RTM if needed.
 Communication with two FEB using RCE platform 10/10Use dev RTM if needed.
 Readout of multiple hybrids on two FEB using RCE platform 10/17Use dev RTM if needed.

 

Readout of multiple (>2) FEB each with multiple hybrids.

 10/24Need HPS RTM. Preferrably with new internal cables and breakout board.
 Test of "full"  Commissioning/testing of full RCE platform 1011/137Use all final hardware with increasing number of FEBs/modules.
Shipping Pelle/Matt/Bob  
 SVT Box Design 9/5 
 Procurement/fabrication SVT BoxesBob10/5 
 Assemble SVT BoxesBob10/12 
 Design Spares Boxes 9/12 
 Order standard boxesMarco9/26 
 Pack Boxes   
 Ship boxes