Item/Task | Sub-item/task | Owner | Dates | Comment | ||||
---|---|---|---|---|---|---|---|---|
FEB | Ben | |||||||
layout | Done | |||||||
fabrication | done | |||||||
loading | 8/2629 | |||||||
testing 2 boards | 8/27-9/5 | |||||||
rest of | the batch ready byFE boards fab and loaded | 9/12 | and tested by 9/15||||||
all FE boards tested | 9/19 | |||||||
L4-6 Half-module production | Tim/Omar | |||||||
apv25 loading | done | |||||||
hybrid & sensor QA | done | |||||||
half-module production incl. QA | 9/5 | |||||||
L1-3 Module assembly | Tim/Sho | |||||||
Modules for detector | 9/5 | |||||||
Spares | 9/5 | |||||||
L4-6 Module assembly | Tim/Sho | |||||||
Modules for detector | 9/12 | |||||||
Spares | 9/12 | |||||||
FEB support | Richard | |||||||
Machine slots in support box | ||||||||
Design pockets (need final FE board) | ||||||||
Fabrication and dry assembly | 9/15 | |||||||
Mechanical dry run assembly | Who? | |||||||
w/o cabling and real FEBs (but FEB cold plate) | 9/5 | |||||||
Motion control system check | Takashi | |||||||
Test stages on vac box | 9/5 | |||||||
Connect bottom U channel, set limits, calibrate | 9/12 | conflict with survey? | ||||||
Connect top U channel, set limits, calibrate | 9/12 | |||||||
Survey | Tim/Sho | overview and procedures needed | ||||||
L1-3 module survey | 9/12 | |||||||
L4-6 module survey | 9/12 | |||||||
U-channels survey | 9/12 | Need mounted modules (see below). | ||||||
SVT full assembly survey | 9/22-9/26 | Coordinate with alignment group (see below) | ||||||
Internal cabling | Tim/Dave | |||||||
Magnet wire signal transmission test | done | |||||||
Magnet wire high voltage test | done | Pelle will do it. | ||||||
FEB mezzanine card layout | done | |||||||
FEB mezzanine card fabrication | 9/5 | |||||||
Hybrid mezzanine card layout | 9/5 | |||||||
Hybrid mezzanine card fabrication | 9/5 | |||||||
L1-3 cross-over board design | 9/12 | |||||||
L1-3 cross-over board layout | 9/12 | |||||||
L1-3 cross-over board fabrication & assembly/checkout | 9/12 | |||||||
LV mezzanine card layout | ||||||||
LV mezzanine card fabrication | ||||||||
HV mezzanine card layout | ||||||||
HV mezzanine card fabrication | ||||||||
pre-production bundle assembly | 9/12 | |||||||
pre-production bundle test with FEB | 9/19 | |||||||
production bundle assembly and test | 10/6 | critical path for full assembly (see below) | ||||||
FEB power bundle design (from flange) | done | |||||||
FEB power bundle assembly (from flange) | 8/26 | Need cable length estimate. 2 days of shop work. | ||||||
FEB high voltage bundle design (from flange) | done | |||||||
FEB power bundle assembly (from flange) | 8/26 | Need cable length estimate. 2 days of shop work. | ||||||
FEB data bundle design (to flange) | ||||||||
FEB data bundle assembly (to flange) | ||||||||
External cabling & Power | pelle | |||||||
High voltage | 8/22 | 2/3 bundles done. Waiting for more wire. | ||||||
Low voltage | Done. | |||||||
Fibers | Done. | Between flange and DAQ crate. | ||||||
PS checkout | Done. | |||||||
PS epics control | 9/5 | Can control through backup interface until ready. | ||||||
Power flange | Pelle | |||||||
Flange w/ board assembly | 9/12 | One spare included. | ||||||
Testing with FEB and PS | 9/12 | Need dummy connector on power. High voltage with banana plugs? | ||||||
Signal flange | Pelle | |||||||
Board fabrication (5 boards) | Done. | |||||||
Board prepping | Done. | |||||||
Board testing | Done. | Needs Ben for high-speed tests. | ||||||
Flange w/ board assembly | 8/20-8/27 | Potting. | ||||||
Board fabrication (spares) | 9/5 | |||||||
Board loading (spares) | 9/5 | |||||||
Board testing (spares) | 9/5 | Needs Ben for high-speed tests | ||||||
Chiller and cooling system | Marco | 9/12 | ||||||
Target | Clive/Marco | |||||||
Design | 9/5 | |||||||
Fabrication | 9/19 | |||||||
Testing | 9/26 | |||||||
Wire frame holder | Clive/Marco/Takashi | |||||||
Design | done | |||||||
Fabrication | 9/12 | Wire Stretching | ||||||
Testing | 9/12 | Mechanical dry run assembly | ||||||
Shawn | U-supports, FEB cold plate, stages | 8/8 | ||||||
Define cable lengths for power and HV bundles | 8/8 | Motion control system check | ||||||
Final SVT Assembly | Takashi | 8/15 | Mechanical assembly | |||||
Mount modules in U-channels | 9/22 | |||||||
Dress modules in U-channels with cabling | 9/26 | cabling not ready? | ||||||
Assemble FEBs on cooling plate and dress with cables | 10/17 | cables are ready 10/6 Need 11 days? | ||||||
Full SVT assembly including stages | 10/22 | Ready for full system | ||||||
ATCA/RCE Platform hardware | Ryan/Pelle | |||||||
RTM layout | done | After testing trigger interface at JLab. | ||||||
RTM fabrication & loading | done | |||||||
RTM checkout | 9/5 | |||||||
SVT DAQ commissioning | Ryan/Ben | |||||||
Commissioning of RCE platform with multiple FEBs and hybrids | 9/8-9/19 | Need: flanges, FEBs and hybrids. Can be done with spares if interfering with assembly. | ||||||
Commissioning/testing of full RCE platform | 10/20 | Use all final hardware with increasing number of FEBs/modules. | ||||||
Shipping | Pelle/Matt | |||||||
Box design | 8/29 | Nr of boxes, isolator requirements for transport of delicate modules | ||||||
Procurement/fabrication | 9/19 | |||||||
Assembly | 10/3 |