Item/Task | Sub-item/task | Owner | Dates | Comment | |
---|---|---|---|---|---|
FEB | Ben | ||||
layout | Done 8/4 | ||||
fabrication | 8/6-8/12done | ||||
loading | 8/13-8/2026 | ||||
testing 2 boards | 8/2127- 9/5 | rest of the batch ready by 9/12 and tested by 9/15 | |||
L4-6 Half-module production | Tim | ||||
apv25 loading | 8/7done | ||||
hybrid & sensor QA | 8/12done | ||||
half-module production incl. QA | 8/19-8/29 | 9/5 | When Tim is back. | ||
L1-3 Module assembly | Tim | 8/18-8/29 | |||
Modules for detector | 8/18-8/29 9/5 | ||||
Spares | 9/1-9/5 | ||||
L4-6 Module assembly | Tim | 8/18-8/29 | |||
Modules for detector | 8/18-8/299/12 | ||||
Spares | 9/1-9/512 | ||||
FEB support | ShawnRichard | ||||
Machine slots in support box | 8/8 | ||||
Design pockets | 8/21-8/29 | Need loaded FEB for design | |||
Fabrication and dry assembly | 9/1-9/515 | ||||
Mechanical dry run assembly | |||||
w/o cabling and real FEBs (but FEB cold plate) | 89/85 | ||||
Motion control system check | Takashi | 89/155 | |||
Survey | overview and procedures needed | ||||
L1-3 module survey | 9/1-9/512 | ||||
L4-6 module survey | 9/8-9/12 | ||||
U-channels survey | 9/8-9/12 | Need mounted modules (see below). | |||
SVT full assembly survey | 9/22-9/26 | ||||
Internal cabling | Tim/Dave | ||||
Magnet wire signal transmission test | done | ||||
Magnet wire high voltage test | 8/8done | Pelle will do it. | |||
FEB mezzanine card layout | 8/8done | ||||
FEB mezzanine card fabrication | 89/155 | ||||
Hybrid mezzanine card layout | 89/135 | ||||
Hybrid mezzanine card fabrication | 89/205 | ||||
L1-3 cross-over board design | 8/18-8/229/12 | ||||
L1-3 cross-over board layout | 8/25-8/299/12 | ||||
L1-3 cross-over board fabrication & assembly/checkout | 9/1-9/1012 | ||||
pre-production bundle assembly | 8/21-8/269/12 | ||||
pre-production bundle test with FEB | 8/27-9/319 | ||||
production bundle assembly | 9/4-9/1210/6 | ||||
FEB power bundle design (from flange) | done | ||||
FEB power bundle assembly (from flange) | 8/26 | Need cable length estimate. 2 days of shop work. | |||
FEB high voltage bundle design (from flange) | done | ||||
FEB power bundle assembly (from flange) | 8/26 | Need cable length estimate. 2 days of shop work. | |||
External cabling & Power | pelle | ||||
High voltage | 8/22 | 2/3 bundles done. Waiting for more wire. | |||
Low voltage | Done. | ||||
Fibers | Done. | Between flange and DAQ crate. | |||
PS checkout | Done. | ||||
PS epics control | 9/15 | Can control through backup interface until ready. | |||
Power flange | Pelle | ||||
Flange w/ board assembly | 89/812 | One spare included. | |||
Testing with FEB and PS | 89/812 | Need dummy connector on power. High voltage with banana plugs? | |||
Signal flange | Pelle | ||||
Board fabrication (5 boards) | Done. | ||||
Board prepping | 5 | /8-8/8 Done. | |||
Board testing | 8 | /18-8/19Done. | Needs Ben for high-speed tests. | ||
Flange w/ board assembly | 8/20-8/27 | Potting. | |||
Board fabrication (spares) | 8/20-8/279/5 | ||||
Board loading (spares) | 8/28-9/45 | ||||
Board testing (spares) | 9/5-9/6 | Needs Ben for high-speed tests | |||
Chiller and cooling system | Marco | 9/12 | |||
Target | Clive/Marco | ||||
Design | 8/6-8/159/5 | ||||
Fabrication | 8/18-8/229/19 | ||||
Testing | 8/25-89/26 | ||||
Wire frame holder | Clive/Marco/Takashi | ||||
Design | 8/6-8/15done | ||||
Fabrication | 8/18-8/22 | 9/12 | Wire Stretching | ||
Testing | 8/25-8/269/12 | ||||
Mechanical dry run assembly | Shawn | ||||
U-supports, FEB cold plate, stages | 8/8 | ||||
Define cable lengths for power and HV bundles | 8/8 | ||||
Motion control system check | Takashi | 8/15 | |||
Mechanical assembly | |||||
Mount modules in U-channels | 9/1-9/522 | ||||
Dress modules in U-channels with cabling | 9/15-9/1926 | ||||
Assemble FEBs on cooling plate and dress with cables | 9/15-9/1910/17 | ||||
Full SVT assembly including stages | 9/15-9/1910/22 | ||||
ATCA/RCE Platform hardware | Ryan/Pelle | ||||
RTM layout | 8/15done | After testing trigger interface at JLab. | |||
RTM fabrication & loading | 8/18-9/1done | ||||
RTM checkout | 9/2-9/5 | ||||
SVT DAQ commissioning | Ryan/Ben | ||||
Commissioning of RCE platform with multiple FEBs and hybrids | 9/8-9/19 | Need: flanges, FEBs and hybrids. Can be done with spares if interfering with assembly. | |||
Commissioning/testing of full RCE platform | 9/22-10/320 | Use all final hardware with increasing number of FEBs/modules. | |||
Shipping | Pelle/Matt | ||||
Box design | 8/1529 | Nr of boxes, isolator requirements for transport of delicate modules | |||
Procurement/fabrication | 9/1219 | ||||
Assembly | 910/193 |