Item/Task | Owner | subSub-item/task | Owner | Dates | Comment |
---|---|---|---|---|---|
FEB | Ben | ||||
layout | layout | Done 8/4 | |||
fabrication | fabrication | 8/6-8/12 | |||
loading | loading | 8/13-8/20 | |||
testing | testing | 8/21- | |||
L4-6 Half-module production | TimTim | ||||
apv25 loading | 8/7 | ||||
hybrid & sensor QA | 8/12 | ||||
half-module production incl. QA | 8/19-8/29 | When Tim is back. | |||
L1-3 Module assembly | Tim | ||||
L4-6 Module assembly | Tim | ||||
Mechanical dry run assemblyShawn | |||||
w/o cabling and real FEBs (but cold plate) | 8/8 | ||||
Motion control system check | Takashi | 8/15 | |||
Survey | Tim/Takashi/John | overview and procedures needed | |||
Modules | |||||
U-channels | |||||
SVT full assembly survey | |||||
Internal cabling | Tim/Dave | ||||
Magnet wire signal transmission test | done | ||||
Magnet wire high voltage test | 8/8 | Pelle will do it. | |||
FEB mezzanine card layout | 8/8 | ||||
FEB mezzanine card fabrication | 8/15 | ||||
Hybrid mezzanine card layout | 8/13 | ||||
Hybrid mezzanine card fabrication | 8/20 | ||||
pre-production bundle assembly | 8/21-8/26 | ||||
pre-production bundle test with FEB | 8/27-9/3 | ||||
production bundle assembly | 9/4-9/12 | ||||
FEB power bundle design | done | ||||
FEB power bundle assembly | 8/26 | Need cable length estimate. 2 days of shop work. | |||
FEB high voltage bundle design | done | ||||
FEB power bundle assembly | 8/26 | Need cable length estimate. 2 days of shop work. | |||
External cabling & PowerPelle | pelle | ||||
High voltage | 8/22 | 2/3 bundles done. Waiting for more wire. | |||
Low voltage | Done. | ||||
PS checkout | Done. | ||||
PS epics control | 9/1 | Can control through backup interface until ready. | |||
Power flange | Pelle | ||||
Flange w/ board assembly | Fabrication | 8/8 | One spare included. | ||
Testing with FEB and PS | 8/8 | Need dummy connector on power. High voltage with banana plugs? | |||
Signal flange | Pelle | ||||
Board fabrication (5 boards) | Done. | ||||
Board prepping | Fabrication | 5/8-8/8 | |||
Board testing | 8/18-8/19 | Needs Ben for high-speed tests. | |||
Flange w/ board assembly | 8/20-8/27 | Potting. | |||
Board fabrication (spares) | 8/20-8/27 | ||||
Board loading (spares) | 8/28-9/4 | ||||
Board testing (spares) | 9/5-9/6 | Needs Ben for high-speed tests | |||
Chiller and cooling system | Marco | ||||
Target | Clive/Marco | ||||
Design | |||||
Fabrication | |||||
Testing | |||||
Shipping | Pelle/Matt | ||||
Box design | 8/12 | Nr of boxes, isolator requirements for transport of delicate modules | |||
Procurement/fabrication | 9/12 | ||||
Assembly |
...
9/19 |