Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
layoutfabricationTim
Item/TaskOwnersubSub-item/taskOwnerDatesComment
FEB
 
Ben  
  layout 

Done 8/4

 
 fabrication 8/6-8/12 
 loading loading8/13-8/20 
 testing testing8/21- 
L4-6 Half-module production  Tim  
 apv25 loading 8/7 
  hybrid & sensor QA 8/12 
  half-module production incl. QA 8/19-8/29When Tim is back.
L1-3 Module assembly Tim   
L4-6 Module assembly Tim   
Mechanical dry run assemblyShawn    
 w/o cabling and real FEBs (but cold plate) 8/8 
Motion control system check Takashi 8/15 
SurveyTim/Takashi/John   overview and procedures needed
  Modules   
 U-channels   
 SVT full assembly survey   
Internal cabling Tim/Dave   
  Magnet wire signal transmission test done 
  Magnet wire high voltage test 8/8Pelle will do it.
  FEB mezzanine card layout 8/8  
 FEB mezzanine card fabrication 8/15 
  Hybrid mezzanine card layout 8/13  
 Hybrid mezzanine card fabrication 8/20 
  pre-production bundle assembly 8/21-8/26 
  pre-production bundle test with FEB 8/27-9/3  
 production bundle assembly 9/4-9/12  
 FEB power bundle design done  
 FEB power bundle assembly 8/26Need cable length estimate. 2 days of shop work.
  FEB high voltage bundle design done 
  FEB power bundle assembly 8/26Need cable length estimate. 2 days of shop work.
External cabling & PowerPelle  pelle  
 High voltage 8/222/3 bundles done. Waiting for more wire. 
 Low voltage Done.  
 PS checkout Done. 
  PS epics control 9/1Can control through backup interface until ready.
Power flange Pelle  
  Flange w/ board assembly Fabrication8/8One spare included. 
 Testing with FEB and PS 8/8Need dummy connector on power. High voltage with banana plugs?
Signal flange Pelle  
 Board fabrication (5 boards) Done. 
 Board prepping Fabrication5/8-8/8 
 Board testing 8/18-8/19Needs Ben for high-speed tests.
 Flange w/ board assembly 8/20-8/27Potting.
 Board fabrication (spares) 8/20-8/27 
 Board loading (spares) 8/28-9/4 
 Board testing (spares) 9/5-9/6Needs Ben for high-speed tests
Chiller and cooling system  Marco  
     
     
Target Clive/Marco  
  Design   
 Fabrication   
 Testing    
Shipping  Pelle/Matt  
  Box design  8/12Nr of boxes, isolator requirements for transport of delicate modules 
  Procurement/fabrication  9/12 
  Assembly   

...

9/19