Page History
...
- The DS1 detector was rebuilt on March 12-17 2014.
- Thus for the DS1:
- the Milathianaki experiment and later should use the 2014-03-19 metrology
- the Yachandra experiment and earlier should use the previous 2013-12-20 metrology
- The DS2 should use the 2013-12-12 metrology
2014-05-15-CSPAD-CXI-DS1-Metrology.xlsx
2014-05-15-CSPAD-CXI-DS2-Metrology.xlsx
References
- CSPAD Alignment
- CSPad2x2 Alignment
- CSPAD Geometry and Alignment
- CSPAD Geometry SoftwareThe DS1 detector was rebuilt on March 12-17 2014.
Thus for the DS1:
- the Milathianaki experiment and later should use the 2014-03-19 metrology
- the Yachandra experiment and earlier should use the previous 2013-12-20 metrology
The DS2 should use the 2013-12-12 metrology
Overview
Content Tools