Consolidation of the Beamline Schedule (Marco, Stepan)
The current baseline considers the HPS experiment installed inside the alcove downstream the CLAS12 experiment in Hall-B. This decision was taken after consultation with the JLAB management, but after the submission of the proposal in May'13. An addendum to the propsal (here) and an implementation plan (here) were developed to describe the feasibility as well as the impact on the schedule of both experiments. The old schedule as described in the poposal and presented at the DOE Review in July is available herehttps://confluence.slac.stanford.edu/display/hpsg/HPS+DOE+Review%2C+July+11%2C+2013here