Last 365 days: For each monitoring node, for each metric, it is taking around 1 hour to load the data into the repository. Hence, for 80 monitoring nodes, for the 11 metrics, it is going to take approximately 880 hours (36 days). Thus, impracticable amount of time.

...

It is taking a huge amount of time to load the entire data. We must optimize this process. The project is being adjusted to be easier parallelizable in independent processes and each process is being investigated to try to gain some minutes.

Measure time and space taken to load the repository.

...

Wiki Markup
\[3\] PingER Node Details. Retrieved from [https://confluence.slac.stanford.edu/display/IEPM/PingER+NODEDETAILS|../../../../../../../../../display/IEPM/PingER+NODEDETAILS||||||||||\||] on June 5, 2013.

...