Date | Action |
---|---|
05/23 | Pre-Planning meeting |
06/?? | Kickoff meeting |
06/11 | Protein model selected |
06/15 | Booth design complete |
07/02 | Conference validation request submitted |
07/09 | 3D printing of protein model starts |
07/16 | Start preparing DOE conference approval request |
08/01* | Freeman order process begins |
08/01 | Handouts Give-aways decided |
08/08 | Booth theme decided |
08/10 | Artwork for handouts give-aways ready |
08/22 | Additional frame elements ordered |
08/25 | Booth logo design ready |
08/27* | SCinet connection order opens |
08/31 | Artwork for shirts ready |
09/03 | Dell shirts ordered |
09/10 | DOE conference approval request submitted |
09/14* | Entry in Exhibitor Directory Listing |
08/14 | Handouts Give-aways ordered |
09/14 | Protein model printed |
09/25* | Deadline for SCinet connection order to avoid $1000 late fee |
09/30 | Additional frame elements delivered |
10/01* | Advance rate deadline for electrical connections |
10/01 | Handouts Give-aways delivered |
10/01 | Shipping crates ordered |
10/10 | Deadline for hotel cancellation without penalty |
10/15 | 3D content ready |
10/15 | Shipping list completed |
10/15 | Protein model assembled |
10/17* | Deadline for early registration |
10/19 | Shipping crates delivered |
10/22 | Display pre-assembly completed |
10/25* | Discount Deadline to Order all Freeman Labor, Furnishings & Services |
10/30 | Packing hardware starts |
11/02 | Packing hardware complete |
11/05 | Hardware ready to be shipped |
11/08 | Direct-to-site shipment arrives |
11/08 | Exhibits Installation 8 am – 5 pm |
11/09 | Exhibits Installation 8 am – 5 pm |
11/10 | Exhibits Installation 8 am – 5 pm |
11/11 | Exhibits Installation 8 am – 5 pm |
11/12 | Booth Cleanup 8 am – 4 pm |
11/12 | Exhibition Opening Gala 7 - 9 pm |
11/13 | Exhibition Open 10am – 6 pm |
11/14 | Exhibition Open 10am – 6 pm |
11/15 | Exhibition Open 10am – 3 pm |
11/15 | Exhibits Dismantling 3pm – midnight |
11/16 | Exhibits Dismantling 8am – noon |
11/16 | Booth hardware shipped back to SLAC |
12/17 | Booth hardware distributed/recycled/disposed |
* | Approximate date based on SC2011 |
...