changes.
| | |
| | As usual we will meet at 10am PST in the SLAC Kavli room, and in VRVS room CenA. |
| | |
| | h2. Agenda |
| | |
| | | * DC2 Numbers |
| | ** 5 Billion background events (almost) generated = 1 day of background |
| | *** 50 Million background events/day after onboard trigger/filter |
| | **** *55 days = 2750 Million (size of background overlay map) |
| | *** Offline cuts = factor of 10 to 100 reduction = 5 million events/day (worst case) for astro server |
| | **** *55 days = 275 million (yikes, lets hope it is closer to 100 reduction) |
| | * New server status. |
| | ** Aliases defined in [SASHOW2FIX:Proposed server usage] are now set up |
| | *** New 300G disks are installed on glast-mysql01, glast-mysql02, glastlnx09 |
| | ** IIS windows servers are ready to go. |
| | *** glast-ground will be repointed soon, should be transparent to everyone except Chuck |
| | * [DC2 Data Server Event Display plans|^Wired Modes.pdf]. |
| | * Status Reports. |